Concrete Footing Calculator
Professional concrete footing calculator for strip, pad, and pier footings. Get instant concrete volume, bag counts, weight, and cost estimates with an optional waste factor.
Footing inputs
Add 0–15% to cover spillage, over-excavation, and subgrade variation.
$/yd^3 is used to estimate total cost.
Bag yields use manufacturer guidance (e.g., 40 lb ≈ 0.30 ft^3, 60 lb ≈ 0.45 ft^3, 80 lb ≈ 0.60 ft^3; 25 kg ≈ 0.012 m^3). Always round up.
How to use this calculator
This professional-grade concrete footing calculator helps builders, engineers, and DIYers estimate concrete volume, bag counts, weight, and optional cost for strip, pad, and pier footings. Enter dimensions that match the selected footing type, include a waste allowance, and optionally add a delivered price to see cost.
Results update immediately after you tap Calculate, so you can test multiple scenarios on site.
Methodology
The tool computes raw volume (L × W × T for strip and pad, segments for piers), applies the waste multiplier, and converts to both cubic feet and cubic yards (US) or cubic meters (Metric). Weight and bag counts rely on standard yields and densities noted in the citation section.
All calculations strictly follow the formulas and data referenced in the formulas section. Use the inputs to reflect your plans, and consult suppliers or engineers before placing material orders.
Glossary of variables
- L: Footing length (strip or pad).
- B: Width of the strip footing.
- W: Width of the pad footing.
- T: Thickness of the footing.
- D: Pier diameter.
- H: Pier height or depth.
- N: Number of discrete footings (pads or piers).
- w: Waste allowance, percent.
- V: Calculated volume before waste.
- Vtotal: Volume after waste.
How it works: step-by-step
Example: strip footing 80 ft long, 2.0 ft wide, 0.75 ft thick, with 10% waste.
- Base volume: V = 80 × 2.0 × 0.75 = 120 ft^3.
- Waste applied: Vtotal = 120 × (1 + 10/100) = 132 ft^3.
- Convert to cubic yards: 132 ÷ 27 ≈ 4.889 yd^3.
- 80 lb bags: ceil(132 / 0.60) = 220 bags.
- Weight: 132 × 150 = 19,800 lb.
If a supplier quotes $150/yd^3 delivered, cost ≈ 4.889 × 150 ≈ $733.35.
Frequently Asked Questions
Do I need to include the footing key or pedestal?
Yes. Include any additional volumes by increasing dimensions or summing separate estimates.
What if the trench is irregular?
Use average dimensions or break the footing into segments and sum the resulting volumes.
How do I switch between cubic yards and cubic meters?
Select the unit system toggle. US shows cubic yards as primary; Metric shows cubic meters. Both systems still show cubic feet to aid comparison.
Are the bag yields guaranteed?
No. Yields vary with compaction, water content, and product line. Verify with the product’s technical data sheet and round up.
Can I use this to size my footings?
No. This tool estimates concrete quantity only. Structural design must comply with codes such as ACI 318 and consider soil conditions.
What waste percentage should I use?
Use 5–10% for small projects and up to 15% for complex forms, odd shapes, or limited access. Lean on contractor experience to adjust.